Main Road Corridor Segment C

Public Information Meeting
APRIL-MAY 2022

This is the second public information meeting for Main Road Corridor, Segment C: Bohicket Road from Maybank Highway to Betsy Kerrison Parkway.

Charleston County is pleased to present six alternatives for consideration. All six of the reasonable alternatives presented meet the purpose of the project.

The project team invites you to review the proposed alternatives presented below and provide feedback. Please submit comments by filling out the form at the bottom of this page, or by clicking the Contact tab at the top of this page. Your comments will help the project team refine the alternatives and make a recommendation of a preferred alternative.

Project Purpose

The purpose of the project is to enhance traffic operations by reducing existing traffic congestion along the Main Road corridor while accommodating future traffic needs.

The primary purpose of the project is to:
  • Reduce congestion (See projected traffic data.)
  • Increase capacity on Main Road/Bohicket Road from Maybank Highway to Betsy Kerrison Parkway.
The secondary purpose of the project is to:

Provide opportunities for bicyclists and pedestrians to safely travel throughout the project area.

Project Background

Charleston County identified funding to improve Main Road in the 2016 Transportation Sales Tax ordinance. At that time, the ordinance listed the project as the US 17 at Main Road flyover and widening Main Road from Bees Ferry Road to Betsy Kerrison Parkway. In an effort to expedite improvements, the County has separated the project into three segments: Segment A, Segment B, and Segment C.

Segment C begins at the intersection of Bohicket Road and Maybank Highway and extends to Betsy Kerrison Parkway. The project team studied several options for the segment, including widening River Road, widening Bohicket Road, and constructing a new road across the island.

Project Development Process

All federally aided projects and/or projects with the need for federal permitting must comply and adhere to the National Environmental Policy Act (NEPA). The NEPA process often takes three (3) to eight (8) years to complete, and requires the following to complete:

  • Public input throughout
  • Technical studies (18)
  • Development of alternatives
  • Analyze alternatives
  • Development of a Preferred Alternative
  • Preparation of a draft environmental assessment
  • Revision of the preferred alternative
  • US Army Corps of Engineers decision

Current Status

Charleston County initially identified five alternatives that meet the purpose and need of the project and presented these alternatives at an Online Public Information Meeting in October-Dec 2020. During the public comment period the public showed a desire for an in-person meeting and the County agreed to hold a second meeting once COVID-19 restrictions were lifted. During this period, public involvement was ongoing and additional alternatives were identified (Alternatives 1a, 6, and 7), and Alternative 2 and Alternative 5 were eliminated from further consideration due to extensive impacts. Six alternatives are being presented for public comment. All six alternatives meet the purpose and need of the project and have varying impacts to natural and human environments. The project team now needs your input on the presented alternatives.

Next Steps

Once the public comment period has ended, the design team will use your input, along with information gathered from preliminary environmental studies, to refine the project alternatives and identify a Preferred Alternative. Once selected, the County will present a Preferred Alternative, at which time the public will have another opportunity to ask questions and provide input on the project. The final design and right-of-way acquisition phase will begin following the second public comment period.

Alternative 1

Bohicket Road Widening ($120-$145 M)

Download PDF
Wetland Impacts
8.4 acres
Stream Impacts
1461 linear feet
Potential Relocations
18
Floodplain Impacts
8 acres
Impacts to Farmlands
of Statewide Significance

40.6 acres

Alternative 1A

Modified Bohicket Road Widening ($65-$80 M)

Download PDF
Wetland Impacts
5.8 acres
Stream Impacts
795 linear feet
Potential Relocations
14
Floodplain Impacts
8 acres
Impacts to Farmlands
of Statewide Significance

29.6 acres

Alternative 3

New Road Location ($170-$195 M)

Download PDF
Wetland Impacts
35.3 acres
Stream Impacts
590 linear feet
Potential Relocations
2
Floodplain Impacts
8.8 acres
Impacts to Farmlands
of Statewide Significance

79.8 acres

Alternative 4

Bohicket Road and New Road Location ($170-$200 M)

Download PDF
Wetland Impacts
34 acres
Stream Impacts
1484 linear feet
Potential Relocations
16
Floodplain Impacts
14.6 acres
Impacts to Farmlands
of Statewide Significance

57.2 acres

Alternative 6

Rational Roads ($40-$50 M)
*This is based on an alternative by Rational Roads; their concept can be found at https://rationalroads.org/

Download PDF
Wetland Impacts
6.5 acres
Stream Impacts
935 linear feet
Potential Relocations
16
Floodplain Impacts
5.3 acres
Impacts to Farmlands
of Statewide Significance

34.6 acres

Alternative 7

The Sea Islands Way ($135-$155M)

Download PDF
Wetland Impacts
9 acres
Stream Impacts
1124 linear feet
Potential Relocations
28
Floodplain Impacts
12.6 acres
Impacts to Farmlands
of Statewide Significance

75.3 acres

Contact Us

The public comment period for the Segment C alternatives is open for 30 days from April 28 through May 27, 2022.

A public comment period was held from April 28 to May 27, 2022, to allow the public to share comments on the Segment C alternatives. The public comment period is now closed.

If you have any questions regarding the public information meeting or to request printed copies of the meeting materials, call Charleston County Public Works at 843-202-6137.

Mail Written Correspondence

Charleston County
Herbert Nimz, P.E.
Charleston County Public Works – Transportation Engineering
4045 Bridge View Drive, Suite B309
North Charleston, SC 29405
843-202-7600

Charleston County Media Contact

Kelsey Barlow
Public Information Officer
P: 843.202.6090
E: kbarlow@charlestoncounty.org

Charleston County Social Media